●Software engineering is the study and an application of engineering to the design,dvelopment,and(71)of software.
(71)A.maintenance
B.service
C.running
D.deployment
参考答案:A
●Cloud computing is a style of computing in which dynamically scalabled often(72)resources are provided as a service over the internet.
(72)A.real
B.rixed
C.actual
D.virtualized
参考答案:D
●The Project Management Triangle is a model of the constraints of project management.These constraints have been listed scope(or quality),(73),and cost
(73)A.resource
B.time
C.plan
D.tool
参考答案:B
●Establishing a project(74)involves listen milestones,activities,and deliverables with intended start and finish dates,of which the scheduling of employees may be an element.
(74)A.cost management plan
B.riskmanagement plan
C.scope management plan
D.management schedule
参考答案:D
●Risk management’s(75)is to assure uncertainty does not deflect the endeavor from the business goals.
(75)A.trend
B.detail
C.objective
D.rule
参考答案:C