2005年5月信息系统项目管理师上午试题[7]

信息系统项目管理师 责任编辑:tywx1982 2008-08-14

添加老师微信

备考咨询

加我微信

摘要:●The(72)techniqueinvolvesusingprojecetcharacteristicsinamathematicalmodeltopredicttotalprojectcost.modelscanbesimpleorcomplex.(72)A.costaggregationB.reserveanalysisC.parametricestimatingD.fundinglimitreconciliarion[答案讨论]●(73)isameasurable,verifiableworkpoduc

● The (72)technique involves using projecet characteristics in a mathematical model to predict total project cost.models can be simple or complex.
(72) A.cost aggregation B.reserve analysis 

C.parametric estimating D.funding limit reconciliarion
   [答案讨论]

(73)is ameasurable,verifiable work poduct such as specification.feasibility study report,detail document,or working prototype
(73) A.milestone B.deliverable C.etc D.BAC
[答案讨论]

(74)are individuals and organizations that are actively involved in the project,or whose interests may be affected as aresult of project execution or project completion;they may also exert influence over the project and its results.
(74) A.controls B.baselines C.project stakeholders  D.project managers
  [答案讨论]

(75)is the process of obtaining the stakeholdrs’formal acceptance of the completed project scope .verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.
(75) A.project acceptance B.scope verification C.scope definition D.WBS Creation
  [答案讨论]