In a project plan, when the project manager schedules activities, he (or she) often uses ( ) method, This method, precedence relationships between activities are represented by circles connected by one or more arrows. The length of the arrow represents the duration of the relevant activity.

问题1选项
A.causality diagram
B.Gantt chart
C.histogram
D.arrow diagram
参考答案: 查看答案 查看解析 查看视频解析 下载APP畅快刷题