The project ( ) processes include: develop project charter, develop project management plan, direct and manage project work, manage project knowledge, monitor and control project work, perform integrated change control and close project or phase.

问题1选项
A.integration management
B.scope management
C.schedule management
D.resource management
参考答案: 查看答案 查看解析 下载APP畅快刷题