The customer asks your project to be completed 6 months earlier than planned. You think this target can be reached by-overlapping project activities. This approach is known as ( ).

问题1选项
A.balance engineering
B.fast-tracking
C.leveling
D.crashing
参考答案: 查看答案 查看解析 查看视频解析 下载APP畅快刷题