2019上半年系统集成项目管理工程师上午真题(八)

系统集成项目管理工程师 责任编辑:胡媛 2019-05-27

添加老师微信

备考咨询

加我微信

摘要:希赛网软考频道小编为大家整理了2019上半年系统集成项目管理工程师上午真题第八部分,供大家参考。

71、 Big data can be described by four characteristics: Volume, Variety, Velocity and Veracity. (  ) refers to the quantity of generated and stored data。

A. Volume

B. Variety

C. Velocity

D. Veracity

72、(  ) is the extension of internet connectivity into physical devices

and everyday objects. Embedded with electronics, internet connectivity, and other forms of hardware (such as sensors), these devices can communicate and interact with others over the Internet, and they can be remotely monitored and controlled.

A.Cloud Computing

B.Internet of Things

C.Block Chain

D.Artificial Intelligence

73、(  )is a process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities。

A. Develop Project Charter

B. Manage Project Knowledge

C. Monitor and Control Project Work

D. Close Project

74、(  ) is a process of developing a detailed description of the project

and product。

A.Collect Requirements

B.Define Scope

C.Validate Scope

D.Control Scope

75、(  )is a process of monitoring the status of the project to update

the project costs and manage changes to the cost baseline。

A.Plan Cost Management

B. Estimate Costs

C.Determine Budget

D.Control Costs


相关推荐:2019上半年系统集成项目管理工程师上午真题及答案

在线题库:系统集成项目管理工程师历年真题自测估分

更多资料
更多课程
更多真题
温馨提示:因考试政策、内容不断变化与调整,本网站提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!

软考备考资料免费领取

去领取