2019下半年信息系统项目管理师综合知识题(八)

信息系统项目管理师 责任编辑:胡媛 2020-09-16

添加老师微信

备考咨询

加我微信

摘要:不少考生在备考软考信息系统项目管理师考试,希赛小编为大家整理了2019下半年信息系统项目管理师综合知识(八),希望对在备考信息系统项目管理师考试的考生有所帮助。

信息系统项目管理师综合知识在上午考试,希赛小编为大家整理了2019下半年信息系统项目管理师综合知识题(八),供考生备考练习。

71、()seeks to perform root cause investigation as to what is leading identified trends.

A、Problem management

B、Incident management

C、Change management

D、Knowledge management

72、()provides guidance for the development and improvement of capabilities for introducing new and changed service into supported environment.

A、Service strategy

B、Service transition

C、Service design

D、Service operation

73、( )is the process of managing procurement relationships , monitoring contract performance, and making changes and corrections as appropriate,and closing out contracts.

A、Control Procurements

B、Conduct Procurements

C、plan Procurements management

D、Procurements strategy

74、The( )is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables.

A、project scope statement

B、work package

C、WBS

D、project scope plan

75、Risk( )acknowledge the existence of a threat,but no proactive action is taken.

A、avoidance

B、transfer

C、mitigate

D、acceptance

试题练习:历年真题每日一练  |  在线试题库

备考资料:视频课程学习资料  |  免费课程

更多资料
更多课程
更多真题
温馨提示:因考试政策、内容不断变化与调整,本网站提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!

软考备考资料免费领取

去领取