2018上半年软考信息系统监理师英语选择题

软考 责任编辑:胡媛 2018-08-04

添加老师微信

备考咨询

加我微信

摘要:2018上半年软考信息系统监理师考试已结束,相信大家都很关注英语选择题的考试内容,希赛小编就为大家整理了软考信息系统监理师英语选择题供大家参考。

●The information is circulated through communication processes._(71)is not included in Work Performance Information.

(71) A. The status of deliverables

B. Implementation status for change requests

C. Forecasted estimates to complete

D. Work performance report

●(72) is not included in Information Security Risk Assessment Process.

(72) A. Establishing information security risk criteria

B. Identifying the information security risks

C. Formulating an information security risk treatment plan

D. Analysing the information security risk

(73) is not included in Perform Integrated Change Control Process.

(73) A. Defining subsidiary plans

B. Approving changes

C. Managing changes to deliverables

D. Reviewing all change requests

●Every documented change request needs to be ei ther approved or rejected by a responsible individual sually(74).

(74) A. the project sponsor

B. an individual

c. any stakeholeder

D. quality controller

●_(75)in not inc1uded in Control Quality input documents.

(75) A. Project management plan

B. Project documents

C. Quality problems report

D. Work performance data


点击注册会员>>>即可获取信息系统监理师免费在线真题、观看免费公开课!

软考报名:2018下半年软考各地区报名时间汇总

真题自测:软考各科目历年真题及答案解析

更多资讯可关注希赛网软考频道,问题咨询请拨打客服电话400-111-9811

更多资料
更多课程
更多真题
温馨提示:因考试政策、内容不断变化与调整,本网站提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!

软考备考资料免费领取

去领取